OPTIMIZATION OF DIAGRAMS ON USAGE OF POTENTIAL FUEL-GAS ENERGY OF CROSS-COUNTRY PIPE-LINES

Abstract

The paper considers a combined power installation being a part of gas expansion set and thermal engine for gas distribution stations. It is shown that in the case when a steam turbine condensing power plant serves as a substitution station increased heating of gas prior to GES without its cooling after the set is more profitable.

About the Authors

A. D. Kachan

Belarus

Professor, PhD in Engineering



V. M. Kopko
Belarusian National Technical University
Belarus

Professor, PhD in Engineering



S. A. Kachan
Belarusian National Technical University
Belarus
Doctor of Engineering


V. I. Kravzov
Beltransgaz
Belarus

Engineer



References

1. Оптимизация режимов работы турбодетандерной установки с учетом гидратообразования: Разработка технических предложений, направленных на уменьшение сжигаемого газа или исключение сжигания его в подогревателе: Техн. отчет / НТЦ «НЭЭ» НАН Беларуси. – Мн., 1992.

2. Сташок А. Н., ШелестюкА. И. Газотурбинные двигатели НПП «Машпроект» для электростанций: Опыт и новые энергосберегающие технологии // Известия инженерных наук Украины. – 1999. – Вып. 1. – С. 52–57.


Review

For citations:


Kachan A.D., Kopko V.M., Kachan S.A., Kravzov V.I. OPTIMIZATION OF DIAGRAMS ON USAGE OF POTENTIAL FUEL-GAS ENERGY OF CROSS-COUNTRY PIPE-LINES. ENERGETIKA. Proceedings of CIS higher education institutions and power engineering associations. 2005;(3):54-59. (In Russ.)

Views: 1520


Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 License.


ISSN 1029-7448 (Print)
ISSN 2414-0341 (Online)